Graiguenamanagh Fire Station – 9 weeks ahead of schedule

  • 8th May 2018
Graiguenamanagh-Fire-Station2
1024 650 McStan

This project consisted of the building of a new Fire Station to Graiguenamanagh.

The project consisted of full steel endoskeleton fabrication, concrete block construction to achieve high U value rating, installation of all new floor finishes, full mechanical and electrical installation, painting and decoration, and new high specification interior finishes.

The project was successfully completed in 16 weeks.

error: Content is protected !!