Project Description

This project consisted of the building of a new Fire Station to Graiguenamanagh.

Project Features

The project consisted of full steel endoskeleton fabrication, concrete block construction to achieve high U value rating, installation of all new floor finishes, full mechanical and electrical installation, painting and decoration, and new high specification interior finishes.

Programme

The project was successfully completed in 16 weeks.